| 1 | 
					2024-05-31 | 
					Total Pembelian Material Tahap 1 | 
					1,00 | 
					  | 
					497.248.273,00 | 
					497.248.273,00 | 
					497.248.273,00 | 
					
					| 2 | 
					2024-06-10 | 
					Bambu | 
					100,00 | 
					Batang | 
					14.000,00 | 
					1.400.000,00 | 
					498.648.273,00 | 
					
					| 3 | 
					2024-06-10 | 
					Paku 7 CM | 
					10,00 | 
					KG | 
					20.000,00 | 
					200.000,00 | 
					498.848.273,00 | 
					
					| 4 | 
					2024-06-10 | 
					Paku 10 CM | 
					10,00 | 
					KG | 
					20.000,00 | 
					200.000,00 | 
					499.048.273,00 | 
					
					| 5 | 
					2024-06-10 | 
					Kaso 4 X 6 | 
					3,00 | 
					Ikat | 
					155.000,00 | 
					465.000,00 | 
					499.513.273,00 | 
					
					| 6 | 
					2024-06-10 | 
					Besi Lulir 16 mm | 
					48,00 | 
					Batang | 
					184.300,00 | 
					8.846.400,00 | 
					508.359.673,00 | 
					
					| 7 | 
					2024-06-10 | 
					Besi Lulir 13 mm | 
					24,00 | 
					Batang | 
					120.000,00 | 
					2.880.000,00 | 
					511.239.673,00 | 
					
					| 8 | 
					2024-06-10 | 
					Bendrat | 
					20,00 | 
					KG | 
					14.000,00 | 
					280.000,00 | 
					511.519.673,00 | 
					
					| 9 | 
					2024-06-10 | 
					Tips Penurunan Besi | 
					1,00 | 
					Orang | 
					25.000,00 | 
					25.000,00 | 
					511.544.673,00 | 
					
					| 10 | 
					2024-06-12 | 
					Pipa 1 Inc | 
					7,00 | 
					Kg | 
					14.800,00 | 
					103.600,00 | 
					511.648.273,00 | 
					
					| 11 | 
					2024-06-12 | 
					Jasa potong besi kunci | 
					1,00 | 
					Biji | 
					50.000,00 | 
					50.000,00 | 
					511.698.273,00 | 
					
					| 12 | 
					2024-06-15 | 
					Pipa Rucika 3 In | 
					3,00 | 
					Batang | 
					195.000,00 | 
					585.000,00 | 
					512.283.273,00 | 
					
					| 13 | 
					2024-06-15 | 
					Mata kating | 
					1,00 | 
					Dus | 
					100.000,00 | 
					100.000,00 | 
					512.383.273,00 | 
					
					| 14 | 
					2024-06-15 | 
					Kawat Las | 
					1,00 | 
					Dus | 
					85.000,00 | 
					85.000,00 | 
					512.468.273,00 | 
					
					| 15 | 
					2024-06-15 | 
					Besi Polos 8 Full | 
					40,00 | 
					Batang | 
					45.504,00 | 
					1.820.160,00 | 
					514.288.433,00 | 
					
					| 16 | 
					2024-06-15 | 
					Bayar Tukang dan Kenek | 
					5,00 | 
					Hari | 
					330.000,00 | 
					1.650.000,00 | 
					515.938.433,00 | 
					
					| 17 | 
					2024-06-16 | 
					Bayar Pak Nana Bantu tukang | 
					1,00 | 
					Orang | 
					200.000,00 | 
					200.000,00 | 
					516.138.433,00 | 
					
					| 18 | 
					2024-06-23 | 
					Bayar Pak Nana Bantu tukang | 
					4,00 | 
					Orang | 
					50.000,00 | 
					200.000,00 | 
					516.338.433,00 | 
					
					| 19 | 
					2024-06-26 | 
					Beli Triplek | 
					48,00 | 
					Lembar | 
					135.000,00 | 
					6.480.000,00 | 
					522.818.433,00 | 
					
					| 20 | 
					2024-06-26 | 
					Tips Penurunan Triplek | 
					1,00 | 
					Orang | 
					20.000,00 | 
					20.000,00 | 
					522.838.433,00 | 
					
					| 21 | 
					2024-06-27 | 
					Kaso 4 X 6 | 
					192,00 | 
					Batang | 
					36.000,00 | 
					6.912.000,00 | 
					529.750.433,00 | 
					
					| 22 | 
					2024-06-27 | 
					Kaso 4 X 6 | 
					4,00 | 
					Ikat | 
					150.000,00 | 
					600.000,00 | 
					530.350.433,00 | 
					
					| 23 | 
					2024-06-27 | 
					Paku 4 Cm | 
					4,00 | 
					KG | 
					25.000,00 | 
					100.000,00 | 
					530.450.433,00 | 
					
					| 24 | 
					2024-06-27 | 
					Tips Pengiriman Kayu | 
					1,00 | 
					Orang | 
					20.000,00 | 
					20.000,00 | 
					530.470.433,00 | 
					
					| 25 | 
					2024-06-30 | 
					Beli kopi buat tukang | 
					1,00 | 
					Pack | 
					50.000,00 | 
					50.000,00 | 
					530.520.433,00 | 
					
					| 26 | 
					2024-06-30 | 
					Beli skrup gypsum | 
					3,00 | 
					Box | 
					85.000,00 | 
					255.000,00 | 
					530.775.433,00 | 
					
					| 27 | 
					2024-06-30 | 
					Beli mata skrup | 
					1,00 | 
					Pcs | 
					15.000,00 | 
					15.000,00 | 
					530.790.433,00 | 
					
					| 28 | 
					2024-06-30 | 
					Beli benang | 
					3,00 | 
					Pcs | 
					5.000,00 | 
					15.000,00 | 
					530.805.433,00 | 
					
					| 29 | 
					2024-06-30 | 
					Bayar tukang dan kenek | 
					9,00 | 
					Hari | 
					330.000,00 | 
					2.970.000,00 | 
					533.775.433,00 | 
					
					| 30 | 
					2024-07-01 | 
					Beli kaso 4x6 cm | 
					5,00 | 
					Ikat | 
					150.000,00 | 
					750.000,00 | 
					534.525.433,00 | 
					
					| 31 | 
					2024-07-01 | 
					Tips nurunin kaso | 
					1,00 | 
					Kali | 
					10.000,00 | 
					10.000,00 | 
					534.535.433,00 | 
					
					| 32 | 
					2024-07-02 | 
					Bayar pak Nana bantu tukang | 
					4,00 | 
					Hari | 
					50.000,00 | 
					200.000,00 | 
					534.735.433,00 | 
					
					| 33 | 
					2024-07-02 | 
					Konsumsi tukang 7 hari | 
					7,00 | 
					Hari | 
					15.000,00 | 
					105.000,00 | 
					534.840.433,00 | 
					
					| 34 | 
					2024-07-04 | 
					Beli paku beton 7 cm | 
					2,00 | 
					Dus | 
					30.000,00 | 
					60.000,00 | 
					534.900.433,00 | 
					
					| 35 | 
					2024-07-04 | 
					Beli paku 4 cm | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					534.920.433,00 | 
					
					| 36 | 
					2024-07-05 | 
					Pembuatan spanduk Pembangunan Masjid | 
					3,00 | 
					Pcs | 
					162.666,67 | 
					488.000,00 | 
					535.408.433,00 | 
					
					| 37 | 
					2024-07-06 | 
					Beli sekrup 5 L | 
					4,00 | 
					Kg | 
					80.000,00 | 
					320.000,00 | 
					535.728.433,00 | 
					
					| 38 | 
					2024-07-06 | 
					Beli paku 4 cm 1/2 kg | 
					0,50 | 
					Kg | 
					30.000,00 | 
					15.000,00 | 
					535.743.433,00 | 
					
					| 39 | 
					2024-07-06 | 
					Konsumsi kerja bakti Pembangunan Masjid | 
					1,00 | 
					Hari | 
					50.000,00 | 
					50.000,00 | 
					535.793.433,00 | 
					
					| 40 | 
					2024-07-06 | 
					Bayar pak Nana bantu tukang | 
					7,00 | 
					Hari | 
					50.000,00 | 
					350.000,00 | 
					536.143.433,00 | 
					
					| 41 | 
					2024-07-07 | 
					Bayar tukang dan kenek | 
					5,00 | 
					Hari | 
					330.000,00 | 
					1.650.000,00 | 
					537.793.433,00 | 
					
					| 42 | 
					2024-07-10 | 
					Beli pralon rucika 3/4 inch | 
					4,00 | 
					Batang | 
					45.000,00 | 
					180.000,00 | 
					537.973.433,00 | 
					
					| 43 | 
					2024-07-10 | 
					Beli keni 3/4 inch | 
					2,00 | 
					Buah | 
					5.000,00 | 
					10.000,00 | 
					537.983.433,00 | 
					
					| 44 | 
					2024-07-12 | 
					Beli paku 7 cm | 
					5,00 | 
					Kg | 
					20.000,00 | 
					100.000,00 | 
					538.083.433,00 | 
					
					| 45 | 
					2024-07-12 | 
					Beli paku 5 cm | 
					2,00 | 
					Kg | 
					20.000,00 | 
					40.000,00 | 
					538.123.433,00 | 
					
					| 46 | 
					2024-07-13 | 
					Beli kaso 4x6 cm | 
					16,00 | 
					Ikat | 
					150.000,00 | 
					2.400.000,00 | 
					540.523.433,00 | 
					
					| 47 | 
					2024-07-13 | 
					Beli kaso 4x6 cm | 
					18,00 | 
					Batang | 
					36.000,00 | 
					648.000,00 | 
					541.171.433,00 | 
					
					| 48 | 
					2024-07-13 | 
					Beli paku 5 cm | 
					5,00 | 
					Kg | 
					20.000,00 | 
					100.000,00 | 
					541.271.433,00 | 
					
					| 49 | 
					2024-07-14 | 
					Beli kopi buat tukang | 
					1,00 | 
					Kali | 
					77.500,00 | 
					77.500,00 | 
					541.348.933,00 | 
					
					| 50 | 
					2024-07-14 | 
					Bayar kenek | 
					5,00 | 
					Hari | 
					195.000,00 | 
					975.000,00 | 
					542.323.933,00 | 
					
					| 51 | 
					2024-07-14 | 
					Bayar pak Nana bantu tukang | 
					5,00 | 
					Hari | 
					50.000,00 | 
					250.000,00 | 
					542.573.933,00 | 
					
					| 52 | 
					2024-07-21 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Hari | 
					50.000,00 | 
					50.000,00 | 
					542.623.933,00 | 
					
					| 53 | 
					2024-07-21 | 
					Beli mata bor beton | 
					1,00 | 
					Pcs | 
					20.000,00 | 
					20.000,00 | 
					542.643.933,00 | 
					
					| 54 | 
					2024-07-21 | 
					Beli skrup | 
					1,00 | 
					Dus | 
					65.000,00 | 
					65.000,00 | 
					542.708.933,00 | 
					
					| 55 | 
					2024-07-21 | 
					Bayar pak Nana bantu tukang | 
					3,00 | 
					Hari | 
					50.000,00 | 
					150.000,00 | 
					542.858.933,00 | 
					
					| 56 | 
					2024-07-21 | 
					Bayar kenek 2 orang | 
					3,50 | 
					Hari | 
					300.000,00 | 
					1.050.000,00 | 
					543.908.933,00 | 
					
					| 57 | 
					2024-07-26 | 
					Beli lem beton | 
					5,00 | 
					Botol | 
					60.900,00 | 
					304.500,00 | 
					544.213.433,00 | 
					
					| 58 | 
					2024-07-26 | 
					Beli beton cor | 
					10,00 | 
					Kubik | 
					812.000,00 | 
					8.120.000,00 | 
					552.333.433,00 | 
					
					| 59 | 
					2024-07-26 | 
					Bayar tukang | 
					8,50 | 
					Hari | 
					180.000,00 | 
					1.530.000,00 | 
					553.863.433,00 | 
					
					| 60 | 
					2024-07-26 | 
					Bayar kenek | 
					4,00 | 
					Hari | 
					150.000,00 | 
					600.000,00 | 
					554.463.433,00 | 
					
					| 61 | 
					2024-07-27 | 
					Beli gorengan | 
					1,00 | 
					Kali | 
					50.000,00 | 
					50.000,00 | 
					554.513.433,00 | 
					
					| 62 | 
					2024-07-27 | 
					Beli kopi kapal api, indocafe, rokok dan gula pasir | 
					1,00 | 
					Kali | 
					293.000,00 | 
					293.000,00 | 
					554.806.433,00 | 
					
					| 63 | 
					2024-07-27 | 
					Beli pasir | 
					0,75 | 
					Kijang | 
					126.666,67 | 
					95.000,00 | 
					554.901.433,00 | 
					
					| 64 | 
					2024-07-27 | 
					Tips material | 
					1,00 | 
					Kali | 
					10.000,00 | 
					10.000,00 | 
					554.911.433,00 | 
					
					| 65 | 
					2024-07-27 | 
					Beli es teh | 
					2,00 | 
					Teko | 
					50.000,00 | 
					100.000,00 | 
					555.011.433,00 | 
					
					| 66 | 
					2024-07-27 | 
					Beli nasi | 
					22,00 | 
					Bungkus | 
					15.000,00 | 
					330.000,00 | 
					555.341.433,00 | 
					
					| 67 | 
					2024-08-04 | 
					Beli mata bor skrup | 
					5,00 | 
					Pcs | 
					10.000,00 | 
					50.000,00 | 
					555.391.433,00 | 
					
					| 68 | 
					2024-08-04 | 
					Konsumsi kerja bakti copot papan cor tiang | 
					1,00 | 
					Hari | 
					336.500,00 | 
					336.500,00 | 
					555.727.933,00 | 
					
					| 69 | 
					2024-08-09 | 
					Beli pasir 1/4 mobil buat nutup tembok atas | 
					0,25 | 
					Mobil | 
					400.000,00 | 
					100.000,00 | 
					555.827.933,00 | 
					
					| 70 | 
					2024-08-09 | 
					Beli hebel 20 pcs buat nutup tembok atas | 
					20,00 | 
					Pcs | 
					6.000,00 | 
					120.000,00 | 
					555.947.933,00 | 
					
					| 71 | 
					2024-08-09 | 
					Bayar tukang 1 hari buat nutup tembok atas | 
					1,00 | 
					Hari | 
					180.000,00 | 
					180.000,00 | 
					556.127.933,00 | 
					
					| 72 | 
					2024-10-18 | 
					Konsumsi Rapat Pembangunan | 
					1,00 | 
					Kali | 
					95.000,00 | 
					95.000,00 | 
					556.222.933,00 | 
					
					| 73 | 
					2024-10-19 | 
					Cetak Proposal Pembangunan | 
					3,00 | 
					Bendel | 
					35.000,00 | 
					105.000,00 | 
					556.327.933,00 | 
					
					| 74 | 
					2024-10-27 | 
					Konsumsi rapat pembangunan | 
					1,00 | 
					Kali | 
					114.000,00 | 
					114.000,00 | 
					556.441.933,00 | 
					
					| 75 | 
					2024-11-02 | 
					Konsumsi rapat pembangunan | 
					1,00 | 
					Kali | 
					96.000,00 | 
					96.000,00 | 
					556.537.933,00 | 
					
					| 76 | 
					2024-11-04 | 
					Besi Polos 8 Full | 
					80,00 | 
					Batang | 
					53.000,00 | 
					4.240.000,00 | 
					560.777.933,00 | 
					
					| 77 | 
					2024-11-04 | 
					Mata kating | 
					1,00 | 
					Dus | 
					70.000,00 | 
					70.000,00 | 
					560.847.933,00 | 
					
					| 78 | 
					2024-11-10 | 
					Bayar tukang 6 hari | 
					6,00 | 
					Hari | 
					200.000,00 | 
					1.200.000,00 | 
					562.047.933,00 | 
					
					| 79 | 
					2024-11-10 | 
					Bayar kenek 5 hari | 
					5,00 | 
					Hari | 
					150.000,00 | 
					750.000,00 | 
					562.797.933,00 | 
					
					| 80 | 
					2024-11-14 | 
					Bayar tukang 5 hari | 
					5,00 | 
					Hari | 
					200.000,00 | 
					1.000.000,00 | 
					563.797.933,00 | 
					
					| 81 | 
					2024-11-14 | 
					Bayar kenek 5 hari | 
					5,00 | 
					Hari | 
					150.000,00 | 
					750.000,00 | 
					564.547.933,00 | 
					
					| 82 | 
					2024-11-15 | 
					Beli kopi buat tukang | 
					1,00 | 
					Kali | 
					100.000,00 | 
					100.000,00 | 
					564.647.933,00 | 
					
					| 83 | 
					2024-11-15 | 
					Beli paku beton 7 Cm 2 Kg | 
					2,00 | 
					Kg | 
					65.000,00 | 
					130.000,00 | 
					564.777.933,00 | 
					
					| 84 | 
					2024-11-15 | 
					Beli besi ulir 16 mm full 40 batang | 
					40,00 | 
					Batang | 
					213.000,00 | 
					8.520.000,00 | 
					573.297.933,00 | 
					
					| 85 | 
					2024-11-15 | 
					Beli besi ulir 13 mm full 40 batang | 
					40,00 | 
					Batang | 
					136.000,00 | 
					5.440.000,00 | 
					578.737.933,00 | 
					
					| 86 | 
					2024-11-15 | 
					Beli kunci besi | 
					1,00 | 
					Pcs | 
					65.000,00 | 
					65.000,00 | 
					578.802.933,00 | 
					
					| 87 | 
					2024-11-16 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					80.000,00 | 
					80.000,00 | 
					578.882.933,00 | 
					
					| 88 | 
					2024-11-17 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					150.000,00 | 
					150.000,00 | 
					579.032.933,00 | 
					
					| 89 | 
					2024-11-17 | 
					Beli bambu 100 batang | 
					100,00 | 
					Batang | 
					17.500,00 | 
					1.750.000,00 | 
					580.782.933,00 | 
					
					| 90 | 
					2024-11-23 | 
					Konsumsi kerja bakti iket besi | 
					1,00 | 
					Kali | 
					100.000,00 | 
					100.000,00 | 
					580.882.933,00 | 
					
					| 91 | 
					2024-11-24 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					120.000,00 | 
					120.000,00 | 
					581.002.933,00 | 
					
					| 92 | 
					2024-11-26 | 
					Bayar Tukang 7 Hari | 
					7,00 | 
					Hari | 
					200.000,00 | 
					1.400.000,00 | 
					582.402.933,00 | 
					
					| 93 | 
					2024-11-26 | 
					Bayar Kenek 6 Hari | 
					6,00 | 
					Hari | 
					150.000,00 | 
					900.000,00 | 
					583.302.933,00 | 
					
					| 94 | 
					2024-11-26 | 
					Beli Kawat 12 Kg | 
					12,00 | 
					Kg | 
					23.000,00 | 
					276.000,00 | 
					583.578.933,00 | 
					
					| 95 | 
					2024-11-26 | 
					Beli Paku Beton 7 Cm 1 Dus | 
					1,00 | 
					Dus | 
					65.000,00 | 
					65.000,00 | 
					583.643.933,00 | 
					
					| 96 | 
					2024-11-26 | 
					Beli Kikir Baco 1 Buah | 
					1,00 | 
					Buah | 
					45.000,00 | 
					45.000,00 | 
					583.688.933,00 | 
					
					| 97 | 
					2024-11-27 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					75.000,00 | 
					75.000,00 | 
					583.763.933,00 | 
					
					| 98 | 
					2024-11-30 | 
					Bayar tukang 6 hari | 
					6,00 | 
					Hari | 
					200.000,00 | 
					1.200.000,00 | 
					584.963.933,00 | 
					
					| 99 | 
					2024-11-30 | 
					Bayar kenek 5 hari | 
					5,00 | 
					Hari | 
					150.000,00 | 
					750.000,00 | 
					585.713.933,00 | 
					
					| 100 | 
					2024-11-30 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					50.000,00 | 
					50.000,00 | 
					585.763.933,00 | 
					
					| 101 | 
					2024-12-01 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					82.000,00 | 
					82.000,00 | 
					585.845.933,00 | 
					
					| 102 | 
					2024-12-01 | 
					Konsumsi tukang dan kerja bakti warung Safa | 
					1,00 | 
					Kali | 
					502.000,00 | 
					502.000,00 | 
					586.347.933,00 | 
					
					| 103 | 
					2024-12-08 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					121.000,00 | 
					121.000,00 | 
					586.468.933,00 | 
					
					| 104 | 
					2024-12-08 | 
					Bayar tukang 3 hari | 
					3,00 | 
					Hari | 
					200.000,00 | 
					600.000,00 | 
					587.068.933,00 | 
					
					| 105 | 
					2024-12-08 | 
					Bayar kenek 2 hari | 
					2,00 | 
					Hari | 
					150.000,00 | 
					300.000,00 | 
					587.368.933,00 | 
					
					| 106 | 
					2024-12-08 | 
					Sewa mobil pak Nasir buat angkut hebel | 
					1,00 | 
					Kali | 
					200.000,00 | 
					200.000,00 | 
					587.568.933,00 | 
					
					| 107 | 
					2024-12-12 | 
					Beli bambu 50 batang + tips | 
					50,00 | 
					Batang | 
					18.000,00 | 
					900.000,00 | 
					588.468.933,00 | 
					
					| 108 | 
					2024-12-12 | 
					Beli minum dan cemilan kerja bakti | 
					1,00 | 
					Kali | 
					100.000,00 | 
					100.000,00 | 
					588.568.933,00 | 
					
					| 109 | 
					2024-12-14 | 
					Buat Spanduk Pembangunan Masjid | 
					1,00 | 
					Pcs | 
					165.000,00 | 
					165.000,00 | 
					588.733.933,00 | 
					
					| 110 | 
					2024-12-15 | 
					Bayar Tukang 7 Hari | 
					7,00 | 
					Hari | 
					200.000,00 | 
					1.400.000,00 | 
					590.133.933,00 | 
					
					| 111 | 
					2024-12-15 | 
					Bayar Kenek 5 Hari | 
					5,00 | 
					Hari | 
					150.000,00 | 
					750.000,00 | 
					590.883.933,00 | 
					
					| 112 | 
					2024-12-21 | 
					Tips nurunin kaso | 
					1,00 | 
					Kali | 
					30.000,00 | 
					30.000,00 | 
					590.913.933,00 | 
					
					| 113 | 
					2024-12-21 | 
					Bayar tukang 7 hari | 
					7,00 | 
					Hari | 
					200.000,00 | 
					1.400.000,00 | 
					592.313.933,00 | 
					
					| 114 | 
					2024-12-21 | 
					Bayar kenek 6 hari | 
					6,00 | 
					Hari | 
					150.000,00 | 
					900.000,00 | 
					593.213.933,00 | 
					
					| 115 | 
					2024-12-22 | 
					Konsumsi Kerja Bakti | 
					1,00 | 
					Kali | 
					154.000,00 | 
					154.000,00 | 
					593.367.933,00 | 
					
					| 116 | 
					2024-12-22 | 
					Beli paku 10 cm 1 Kg | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					593.387.933,00 | 
					
					| 117 | 
					2024-12-22 | 
					Beli kawat 1 Kg | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					593.407.933,00 | 
					
					| 118 | 
					2024-12-25 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					99.000,00 | 
					99.000,00 | 
					593.506.933,00 | 
					
					| 119 | 
					2024-12-25 | 
					Konsumsi rapat pembangunan | 
					1,00 | 
					Kali | 
					101.000,00 | 
					101.000,00 | 
					593.607.933,00 | 
					
					| 120 | 
					2024-12-27 | 
					Pembayaran bondek 6 mm 15 lembar (belanja 20.12.24) | 
					15,00 | 
					Lembar | 
					630.000,00 | 
					9.450.000,00 | 
					603.057.933,00 | 
					
					| 121 | 
					2024-12-27 | 
					Bayar pemesanan konsumsi untuk kerja bakti cor 28.12.24 (Makan, kue dan Esteh) | 
					1,00 | 
					Kali | 
					600.000,00 | 
					600.000,00 | 
					603.657.933,00 | 
					
					| 122 | 
					2024-12-27 | 
					Bayar Tukang 3 Hari | 
					3,00 | 
					Hari | 
					200.000,00 | 
					600.000,00 | 
					604.257.933,00 | 
					
					| 123 | 
					2024-12-27 | 
					Konsumsi rapat | 
					1,00 | 
					Kali | 
					60.000,00 | 
					60.000,00 | 
					604.317.933,00 | 
					
					| 124 | 
					2024-12-27 | 
					Bayar air dan kopi tukang di warung Safa | 
					1,00 | 
					Kali | 
					198.000,00 | 
					198.000,00 | 
					604.515.933,00 | 
					
					| 125 | 
					2024-12-27 | 
					Bayar pompa beton | 
					1,00 | 
					Hari | 
					3.000.000,00 | 
					3.000.000,00 | 
					607.515.933,00 | 
					
					| 126 | 
					2024-12-27 | 
					Bayar Beton Cor 12 Kubik | 
					12,00 | 
					Kubik | 
					825.000,00 | 
					9.900.000,00 | 
					617.415.933,00 | 
					
					| 127 | 
					2024-12-28 | 
					Tambah beli konsumsi kerja bakti ngecor (nasi, minuman) | 
					1,00 | 
					Kali | 
					135.000,00 | 
					135.000,00 | 
					617.550.933,00 | 
					
					| 128 | 
					2024-12-28 | 
					Tambah beli beton cor 3 kubik | 
					3,00 | 
					Kubik | 
					825.000,00 | 
					2.475.000,00 | 
					620.025.933,00 | 
					
					| 129 | 
					2024-12-28 | 
					Bayar kenek 5 orang 1 hari | 
					1,00 | 
					Hari | 
					650.000,00 | 
					650.000,00 | 
					620.675.933,00 | 
					
					| 130 | 
					2024-12-28 | 
					Tips supir 3 mobil cor | 
					3,00 | 
					Mobil | 
					20.000,00 | 
					60.000,00 | 
					620.735.933,00 | 
					
					| 131 | 
					2024-12-28 | 
					Tips operator pompa beton 3 orang | 
					3,00 | 
					Orang | 
					200.000,00 | 
					600.000,00 | 
					621.335.933,00 | 
					
					| 132 | 
					2024-12-28 | 
					Tips mobil material | 
					1,00 | 
					Kali | 
					10.000,00 | 
					10.000,00 | 
					621.345.933,00 | 
					
					| 133 | 
					2024-12-29 | 
					Bayar konsumsi kerja bakti ngecor di warung Safa | 
					1,00 | 
					Kali | 
					353.000,00 | 
					353.000,00 | 
					621.698.933,00 | 
					
					| 134 | 
					2024-12-29 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					60.000,00 | 
					60.000,00 | 
					621.758.933,00 | 
					
					| 135 | 
					2024-12-30 | 
					Bayar paku 7 Cm 5 Kg (belanja 20.12.24) | 
					5,00 | 
					Kg | 
					20.000,00 | 
					100.000,00 | 
					621.858.933,00 | 
					
					| 136 | 
					2024-12-30 | 
					Bayar paku 10 Cm 5 Kg (belanja 20.12.24) | 
					5,00 | 
					Kg | 
					20.000,00 | 
					100.000,00 | 
					621.958.933,00 | 
					
					| 137 | 
					2024-12-30 | 
					Bayar paku 4 Cm 3 Kg (belanja 20.12.24) | 
					3,00 | 
					Kg | 
					20.000,00 | 
					60.000,00 | 
					622.018.933,00 | 
					
					| 138 | 
					2024-12-30 | 
					Bayar kaso 4 x 6 Cm 45 batang (belanja 20.12.24) | 
					45,00 | 
					Batang | 
					40.000,00 | 
					1.800.000,00 | 
					623.818.933,00 | 
					
					| 139 | 
					2025-01-01 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					80.000,00 | 
					80.000,00 | 
					623.898.933,00 | 
					
					| 140 | 
					2025-01-04 | 
					Bayar paku 10 cm 2 kg (belanja 20.12.24) | 
					2,00 | 
					Kg | 
					20.000,00 | 
					40.000,00 | 
					623.938.933,00 | 
					
					| 141 | 
					2025-01-04 | 
					Bayar paku 4 cm 1 kg (belanja 20.12.24) | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					623.958.933,00 | 
					
					| 142 | 
					2025-01-04 | 
					Bayar paku 5 cm 1 kg (belanja 20.12.24) | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					623.978.933,00 | 
					
					| 143 | 
					2025-01-04 | 
					Bayar kaso 4 x 6 Cm 25 batang (belanja 20.12.24) | 
					25,00 | 
					Batang | 
					40.000,00 | 
					1.000.000,00 | 
					624.978.933,00 | 
					
					| 144 | 
					2025-01-04 | 
					Bayar paku 7 Cm 1 Kg (belanja 20.12.24) | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					624.998.933,00 | 
					
					| 145 | 
					2025-01-04 | 
					Bayar kawat 1 Kg (belanja 20.12.24) | 
					1,00 | 
					Kg | 
					23.000,00 | 
					23.000,00 | 
					625.021.933,00 | 
					
					| 146 | 
					2025-01-04 | 
					Bayar paku 10 Cm 1 Kg (belanja 20.12.24) | 
					1,00 | 
					Kg | 
					20.000,00 | 
					20.000,00 | 
					625.041.933,00 | 
					
					| 147 | 
					2025-01-04 | 
					Bayar paku 7 Cm 0.5 Kg (belanja 20.12.24) | 
					0,50 | 
					Kg | 
					20.000,00 | 
					10.000,00 | 
					625.051.933,00 | 
					
					| 148 | 
					2025-01-04 | 
					Bayar paku 4 Cm 0.5 Kg (belanja 20.12.24) | 
					0,50 | 
					Kg | 
					20.000,00 | 
					10.000,00 | 
					625.061.933,00 | 
					
					| 149 | 
					2025-01-04 | 
					Bayar kabel jek 1 set (belanja 20.12.24) | 
					1,00 | 
					Set | 
					16.000,00 | 
					16.000,00 | 
					625.077.933,00 | 
					
					| 150 | 
					2025-01-04 | 
					Bayar plastik cor 1 rol (belanja 20.12.24) | 
					1,00 | 
					Rol | 
					130.000,00 | 
					130.000,00 | 
					625.207.933,00 | 
					
					| 151 | 
					2025-01-04 | 
					Bayar ember 10 Pcs (belanja 20.12.24) | 
					10,00 | 
					Pcs | 
					7.000,00 | 
					70.000,00 | 
					625.277.933,00 | 
					
					| 152 | 
					2025-01-04 | 
					Bayar sarung tangan 3 Lusin (belanja 20.12.24) | 
					3,00 | 
					Lusin | 
					25.000,00 | 
					75.000,00 | 
					625.352.933,00 | 
					
					| 153 | 
					2025-01-04 | 
					Bayar gosokan 2 Pcs (belanja 20.12.24) | 
					2,00 | 
					Pcs | 
					15.000,00 | 
					30.000,00 | 
					625.382.933,00 | 
					
					| 154 | 
					2025-01-04 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					61.000,00 | 
					61.000,00 | 
					625.443.933,00 | 
					
					| 155 | 
					2025-01-05 | 
					Beli cemilan buat tukang | 
					1,00 | 
					Kali | 
					80.000,00 | 
					80.000,00 | 
					625.523.933,00 | 
					
					| 156 | 
					2025-01-05 | 
					Cetak proposal pembangunan 2 set (ke-1) | 
					2,00 | 
					Set | 
					32.000,00 | 
					64.000,00 | 
					625.587.933,00 | 
					
					| 157 | 
					2025-01-06 | 
					Bayar Tukang 7 Hari | 
					7,00 | 
					Hari | 
					200.000,00 | 
					1.400.000,00 | 
					626.987.933,00 | 
					
					| 158 | 
					2025-01-06 | 
					Bayar Kenek 7 Hari (Rapelan Minggu Lalu 2 Hari) | 
					7,00 | 
					Hari | 
					150.000,00 | 
					1.050.000,00 | 
					628.037.933,00 | 
					
					| 159 | 
					2025-01-06 | 
					Akomodasi pengambilan uang ke BJB | 
					1,00 | 
					Kali | 
					100.000,00 | 
					100.000,00 | 
					628.137.933,00 | 
					
					| 160 | 
					2025-01-06 | 
					Cetak Proposal Pembangunan Masjid 2 set (ke-2) | 
					2,00 | 
					Set | 
					25.000,00 | 
					50.000,00 | 
					628.187.933,00 | 
					
					| 161 | 
					2025-01-09 | 
					Pesan Stampel Panitia Pembangunan 2 Pcs | 
					2,00 | 
					Pcs | 
					60.000,00 | 
					120.000,00 | 
					628.307.933,00 | 
					
					| 162 | 
					2025-01-11 | 
					Pembayaran Tukang dari tanggal 7-12 jan 25 (6hr) | 
					6,00 | 
					Hari | 
					200.000,00 | 
					1.200.000,00 | 
					629.507.933,00 | 
					
					| 163 | 
					2025-01-11 | 
					Konsumsi kerja bakti | 
					1,00 | 
					Kali | 
					60.000,00 | 
					60.000,00 | 
					629.567.933,00 | 
					
					| 164 | 
					2025-01-11 | 
					Pembayaran kenek dari tanggal 07-12 jan 25 (6 hari) | 
					6,00 | 
					Hari | 
					150.000,00 | 
					900.000,00 | 
					630.467.933,00 | 
					
					| 165 | 
					2025-01-12 | 
					Beli mata bor beton 10 mm 1 pcs | 
					1,00 | 
					Pcs | 
					35.000,00 | 
					35.000,00 | 
					630.502.933,00 | 
					
					| 166 | 
					2025-01-12 | 
					Beli no drop 1 kg 1 kaleng | 
					1,00 | 
					Kaleng | 
					60.000,00 | 
					60.000,00 | 
					630.562.933,00 | 
					
					| 167 | 
					2025-01-12 | 
					Beli stop kran air 1 pcs | 
					1,00 | 
					Pcs | 
					15.000,00 | 
					15.000,00 | 
					630.577.933,00 | 
					
					| 168 | 
					2025-01-12 | 
					Beli knee 3/4 inch 1 pcs | 
					1,00 | 
					Pcs | 
					4.000,00 | 
					4.000,00 | 
					630.581.933,00 | 
					
					| 169 | 
					2025-01-12 | 
					Beli flow shock 3/4 inch 1 pcs | 
					1,00 | 
					Pcs | 
					4.000,00 | 
					4.000,00 | 
					630.585.933,00 | 
					
					| 170 | 
					2025-01-12 | 
					Beli dop 3/4 inch 1 pcs | 
					1,00 | 
					Pcs | 
					4.000,00 | 
					4.000,00 | 
					630.589.933,00 | 
					
					| 171 | 
					2025-01-12 | 
					Beli lem paralon 1 bungkus | 
					1,00 | 
					Bungkus | 
					8.000,00 | 
					8.000,00 | 
					630.597.933,00 | 
					
					| 172 | 
					2025-01-12 | 
					Beli porfic 1 botol | 
					1,00 | 
					Botol | 
					20.000,00 | 
					20.000,00 | 
					630.617.933,00 | 
					
					| 173 | 
					2025-01-13 | 
					Bayar backup kenek 1 hari | 
					1,00 | 
					Hari | 
					120.000,00 | 
					120.000,00 | 
					630.737.933,00 | 
					
					| 174 | 
					2025-01-13 | 
					Bayar air dan kopi tukang di warung Safa | 
					1,00 | 
					Kali | 
					185.000,00 | 
					185.000,00 | 
					630.922.933,00 | 
					
					| 175 | 
					2025-01-14 | 
					Bayar backup kenek 1 hari | 
					1,00 | 
					Hari | 
					150.000,00 | 
					150.000,00 | 
					631.072.933,00 | 
					
					| 176 | 
					2025-01-16 | 
					Pembayaran Material - gosokan 2 pcs | 
					2,00 | 
					Pcs | 
					15.000,00 | 
					30.000,00 | 
					631.102.933,00 | 
					
					| 177 | 
					2025-01-16 | 
					Pembayaran Material - benang 1 pcs | 
					1,00 | 
					Pcs | 
					5.000,00 | 
					5.000,00 | 
					631.107.933,00 | 
					
					| 178 | 
					2025-01-16 | 
					Pembayaran Material - pasir putih | 
					0,50 | 
					Mobil | 
					380.000,00 | 
					190.000,00 | 
					631.297.933,00 | 
					
					| 179 | 
					2025-01-16 | 
					Pembayaran Material - lakban | 
					1,00 | 
					Pcs | 
					17.000,00 | 
					17.000,00 | 
					631.314.933,00 | 
					
					| 180 | 
					2025-01-16 | 
					Pembayaran Material - kerekan | 
					1,00 | 
					Pcs | 
					45.000,00 | 
					45.000,00 | 
					631.359.933,00 | 
					
					| 181 | 
					2025-01-16 | 
					Pembayaran Material - Tambang | 
					10,00 | 
					Meter | 
					4.500,00 | 
					45.000,00 | 
					631.404.933,00 | 
					
					| 182 | 
					2025-01-16 | 
					Pembayaran Material - kawat | 
					2,00 | 
					Kg | 
					23.000,00 | 
					46.000,00 | 
					631.450.933,00 | 
					
					| 183 | 
					2025-01-16 | 
					Pembayaran Material - pipa 3 inchi | 
					1,00 | 
					Meter | 
					35.000,00 | 
					35.000,00 | 
					631.485.933,00 | 
					
					| 184 | 
					2025-01-16 | 
					Pembayaran Material - pasir putih | 
					1,00 | 
					Mobil | 
					370.000,00 | 
					370.000,00 | 
					631.855.933,00 | 
					
					| 185 | 
					2025-01-16 | 
					Pembayaran Material - kawat ayak | 
					1,50 | 
					Meter | 
					20.000,00 | 
					30.000,00 | 
					631.885.933,00 | 
					
					| 186 | 
					2025-01-16 | 
					Pembayaran Material - bata press | 
					350,00 | 
					Pcs | 
					648,57 | 
					227.000,00 | 
					632.112.933,00 | 
					
					| 187 | 
					2025-01-18 | 
					Pembelian konsumsi Tukang | 
					1,00 | 
					Hari | 
					30.000,00 | 
					30.000,00 | 
					632.142.933,00 | 
					
					| 188 | 
					2025-01-18 | 
					Pembayaran tips penurunan material | 
					1,00 | 
					Orang | 
					30.000,00 | 
					30.000,00 | 
					632.172.933,00 | 
					
					| 189 | 
					2025-01-18 | 
					Pembayaran Material - paku | 
					5,00 | 
					Kg | 
					20.000,00 | 
					100.000,00 | 
					632.272.933,00 | 
					
					| 190 | 
					2025-01-18 | 
					Pembayaran Material - kawat | 
					5,00 | 
					Kg | 
					23.000,00 | 
					115.000,00 | 
					632.387.933,00 | 
					
					| 191 | 
					2025-01-18 | 
					Pembayaran Material - gunting baja | 
					1,00 | 
					Pcs | 
					75.000,00 | 
					75.000,00 | 
					632.462.933,00 | 
					
					| 192 | 
					2025-01-18 | 
					Pembayaran Material - besi 7h | 
					45,00 | 
					Batang | 
					53.000,00 | 
					2.385.000,00 | 
					634.847.933,00 | 
					
					| 193 | 
					2025-01-18 | 
					Pembayaran Material - kating | 
					10,00 | 
					Psc | 
					4.500,00 | 
					45.000,00 | 
					634.892.933,00 | 
					
					| 194 | 
					2025-01-18 | 
					Pembayaran Material - benang | 
					2,00 | 
					Meter | 
					5.000,00 | 
					10.000,00 | 
					634.902.933,00 | 
					
					| 195 | 
					2025-01-18 | 
					Pembayaran Material - kawat | 
					3,00 | 
					Kg | 
					23.000,00 | 
					69.000,00 | 
					634.971.933,00 | 
					
					| 196 | 
					2025-01-18 | 
					Pembayaran Material - kayu galar 5*10 | 
					6,00 | 
					Batang | 
					83.000,00 | 
					498.000,00 | 
					635.469.933,00 | 
					
					| 197 | 
					2025-01-18 | 
					Pembayaran Tukang 7 hari (13-19 jan 2025) | 
					7,00 | 
					Hari | 
					200.000,00 | 
					1.400.000,00 | 
					636.869.933,00 | 
					
					| 198 | 
					2025-01-18 | 
					Pembayaran kenek 4 hari (15 - 18 Jan 2025) | 
					4,00 | 
					Hari | 
					150.000,00 | 
					600.000,00 | 
					637.469.933,00 | 
					
					| 199 | 
					2025-01-18 | 
					Konsumsi Rapat Pembangunan Masjid | 
					1,00 | 
					Pcs | 
					380.000,00 | 
					380.000,00 | 
					637.849.933,00 | 
					
					| 200 | 
					2025-01-19 | 
					Pembayaran Kenek 1 hari minggu | 
					1,00 | 
					Hari | 
					150.000,00 | 
					150.000,00 | 
					637.999.933,00 | 
					
					| 201 | 
					2025-01-23 | 
					Pembayaran Tukang 4 hari (20-23 jan 2025) | 
					4,00 | 
					Hari | 
					200.000,00 | 
					800.000,00 | 
					638.799.933,00 | 
					
					| 202 | 
					2025-01-23 | 
					Pembayaran kenek 3 hari | 
					3,00 | 
					Hari | 
					150.000,00 | 
					450.000,00 | 
					639.249.933,00 | 
					
					| 203 | 
					2025-01-24 | 
					Pengeluaran uang rokok tukang perbaikan toren bang udin | 
					1,00 | 
					Hari | 
					50.000,00 | 
					50.000,00 | 
					639.299.933,00 | 
					
					| 204 | 
					2025-01-27 | 
					Pembelian kaleng 140 pcs | 
					140,00 | 
					Pcs | 
					3.500,00 | 
					490.000,00 | 
					639.789.933,00 | 
					
					| 205 | 
					2025-02-17 | 
					AQUADROP | 
					1,00 | 
					1 kaleng | 
					74.000,00 | 
					74.000,00 | 
					639.863.933,00 | 
					
					| 206 | 
					2025-02-17 | 
					LAKBAN SELANG AC | 
					1,00 | 
					1 roll | 
					15.000,00 | 
					15.000,00 | 
					639.878.933,00 | 
					
					| 207 | 
					2025-02-17 | 
					CLEM SELANG PIPA AC | 
					1,00 | 
					1 pak | 
					25.000,00 | 
					25.000,00 | 
					639.903.933,00 | 
					
					| 208 | 
					2025-02-17 | 
					CELENGAN | 
					81,00 | 
					1 dus | 
					3.500,00 | 
					283.500,00 | 
					640.187.433,00 | 
					
					| 209 | 
					2025-02-17 | 
					PLAMIR | 
					1,00 | 
					1 kaleng | 
					65.900,00 | 
					65.900,00 | 
					640.253.333,00 | 
					
					| 210 | 
					2025-02-17 | 
					ROll CAT KECIL | 
					5,00 | 
					5 pcs | 
					5.756,80 | 
					28.784,00 | 
					640.282.117,00 | 
					
					| 211 | 
					2025-02-17 | 
					NO DROP 20 KG | 
					1,00 | 
					1 PAIL | 
					920.000,00 | 
					920.000,00 | 
					641.202.117,00 | 
					
					| 212 | 
					2025-02-17 | 
					KOPI SAFA | 
					1,00 | 
					4 renceng | 
					68.000,00 | 
					68.000,00 | 
					641.270.117,00 | 
					
					| 213 | 
					2025-02-17 | 
					SNACK UNTUK RAPAT | 
					1,00 | 
					1 PAKET | 
					150.000,00 | 
					150.000,00 | 
					641.420.117,00 | 
					
					| 214 | 
					2025-02-17 | 
					LAMPU BUAT DALAM DAN LUAR | 
					1,00 | 
					4 | 
					380.000,00 | 
					380.000,00 | 
					641.800.117,00 | 
					
					| 215 | 
					2025-02-17 | 
					ONGKOS CEK,BONGKAR  PASANG LAMPU | 
					1,00 | 
					5 | 
					150.000,00 | 
					150.000,00 | 
					641.950.117,00 | 
					
					| 216 | 
					2025-02-17 | 
					BESI PENUTUP GOT DAN LAINNYA | 
					1,00 | 
					1 | 
					2.562.000,00 | 
					2.562.000,00 | 
					644.512.117,00 | 
					
					| 217 | 
					2025-02-17 | 
					CAT BESI.KUAS.KENI.KRAN.T KRAN DLL | 
					1,00 | 
					10 | 
					188.000,00 | 
					188.000,00 | 
					644.700.117,00 | 
					
					| 218 | 
					2025-02-18 | 
					NO DROP 20 KG | 
					1,00 | 
					20 kg | 
					920.000,00 | 
					920.000,00 | 
					645.620.117,00 | 
					
					| 219 | 
					2025-02-23 | 
					MAKANAN DAN MINUMAN KERJA BAKTI | 
					1,00 | 
					10 | 
					146.000,00 | 
					146.000,00 | 
					645.766.117,00 | 
					
					| 220 | 
					2025-02-23 | 
					TUKANG 7 HARI | 
					7,00 | 
					200 | 
					200.000,00 | 
					1.400.000,00 | 
					647.166.117,00 | 
					
					| 221 | 
					2025-02-23 | 
					DP PAK BASAR | 
					1,00 | 
					1 | 
					500.000,00 | 
					500.000,00 | 
					647.666.117,00 | 
					
					| 222 | 
					2025-02-23 | 
					KOPI TUKANG | 
					1,00 | 
					5 | 
					97.000,00 | 
					97.000,00 | 
					647.763.117,00 | 
					
					| 223 | 
					2025-02-23 | 
					KOPI TUKANG | 
					1,00 | 
					5 | 
					97.000,00 | 
					97.000,00 | 
					647.860.117,00 | 
					
					| 224 | 
					2025-02-23 | 
					LIST PLAPON PVC | 
					4,00 | 
					10 BATANG | 
					125.000,00 | 
					500.000,00 | 
					648.360.117,00 | 
					
					| 225 | 
					2025-02-23 | 
					PITING LAMPU | 
					1,00 | 
					1 | 
					74.000,00 | 
					74.000,00 | 
					648.434.117,00 | 
					
					| 226 | 
					2025-02-23 | 
					BIIKIN PROPOSAL | 
					5,00 | 
					5 | 
					20.000,00 | 
					100.000,00 | 
					648.534.117,00 | 
					
					| 227 | 
					2025-02-23 | 
					BAYAR PAK BASAR | 
					1,00 | 
					1 | 
					1.000.000,00 | 
					1.000.000,00 | 
					649.534.117,00 | 
					
					| 228 | 
					2025-02-24 | 
					Besi lampu depanbdan samping | 
					1,00 | 
					1 | 
					348.000,00 | 
					348.000,00 | 
					649.882.117,00 | 
					
					| 229 | 
					2025-02-25 | 
					NO DROP | 
					1,00 | 
					1 | 
					206.500,00 | 
					206.500,00 | 
					650.088.617,00 | 
					
					| 230 | 
					2025-02-25 | 
					Dinabol 10 in | 
					20,00 | 
					1 | 
					2.500,00 | 
					50.000,00 | 
					650.138.617,00 | 
					
					| 231 | 
					2025-02-25 | 
					Dinabol 8 in | 
					8,00 | 
					1 | 
					3.000,00 | 
					24.000,00 | 
					650.162.617,00 | 
					
					| 232 | 
					2025-02-26 | 
					Breket ac out dor | 
					1,00 | 
					1 | 
					70.000,00 | 
					70.000,00 | 
					650.232.617,00 | 
					
					| 233 | 
					2025-02-26 | 
					Pembelian lampu 50 what 3 pcs | 
					1,00 | 
					1 | 
					315.000,00 | 
					315.000,00 | 
					650.547.617,00 | 
					
					| 234 | 
					2025-02-26 | 
					Topi lampu dan piting 3 set | 
					1,00 | 
					1 | 
					75.000,00 | 
					75.000,00 | 
					650.622.617,00 | 
					
					| 235 | 
					2025-02-26 | 
					Lampu 15 what | 
					1,00 | 
					1 | 
					20.000,00 | 
					20.000,00 | 
					650.642.617,00 | 
					
					| 236 | 
					2025-02-27 | 
					KERAMIK KIA 50X50 | 
					1,00 | 
					1 | 
					86.500,00 | 
					86.500,00 | 
					650.729.117,00 | 
					
					| 237 | 
					2025-02-27 | 
					No drop 4 kg toko material acun | 
					1,00 | 
					1 | 
					245.000,00 | 
					245.000,00 | 
					650.974.117,00 | 
					
					| 238 | 
					2025-02-27 | 
					BAYAR UPAH PA BASAR | 
					1,00 | 
					1 | 
					500.000,00 | 
					500.000,00 | 
					651.474.117,00 | 
					
					| 239 | 
					2025-02-27 | 
					Roll kecil | 
					1,00 | 
					3 | 
					21.000,00 | 
					21.000,00 | 
					651.495.117,00 | 
					
					| 240 | 
					2025-02-27 | 
					Konsumsi 2 hari kerja bakti dan tukang | 
					1,00 | 
					1 | 
					90.000,00 | 
					90.000,00 | 
					651.585.117,00 | 
					
					| 241 | 
					2025-02-28 | 
					Bayar material tgl 7-1-25 | 
					1,00 | 
					1 | 
					3.969.000,00 | 
					3.969.000,00 | 
					655.554.117,00 | 
					
					| 242 | 
					2025-02-28 | 
					Bayar material tgl 15/1 2025 | 
					1,00 | 
					1 | 
					2.717.000,00 | 
					2.717.000,00 | 
					658.271.117,00 | 
					
					| 243 | 
					2025-02-28 | 
					Seleri pengecetan pak nana | 
					1,00 | 
					1 | 
					500.000,00 | 
					500.000,00 | 
					658.771.117,00 | 
					
					| 244 | 
					2025-02-28 | 
					Upah 2 hari nasir | 
					1,00 | 
					1 | 
					300.000,00 | 
					300.000,00 | 
					659.071.117,00 | 
					
					| 245 | 
					2025-03-02 | 
					Beli pipa dll | 
					1,00 | 
					1 | 
					24.000,00 | 
					24.000,00 | 
					659.095.117,00 | 
					
					| 246 | 
					2025-03-02 | 
					No  drop 4 kg | 
					1,00 | 
					1 | 
					206.500,00 | 
					206.500,00 | 
					659.301.617,00 | 
					
					| 247 | 
					2025-03-10 | 
					Jilid proposal 10 jilid | 
					1,00 | 
					1 | 
					50.000,00 | 
					50.000,00 | 
					659.351.617,00 | 
					
					| 248 | 
					2025-03-11 | 
					NO DROP 4 KG 3 KALENG | 
					1,00 | 
					1 | 
					632.000,00 | 
					632.000,00 | 
					659.983.617,00 | 
					
					| 249 | 
					2025-03-13 | 
					BAYAR NOTA MATERIAL 20/1/25 | 
					1,00 | 
					1 | 
					1.020.500,00 | 
					1.020.500,00 | 
					661.004.117,00 | 
					
					| 250 | 
					2025-03-13 | 
					BAYAR NOTA MATERIAL 22/1/25 | 
					1,00 | 
					1 | 
					904.000,00 | 
					904.000,00 | 
					661.908.117,00 | 
					
					| 251 | 
					2025-03-13 | 
					BAYAR NOTA MATERIAL 6/2 25 | 
					1,00 | 
					1 | 
					494.000,00 | 
					494.000,00 | 
					662.402.117,00 | 
					
					| 252 | 
					2025-03-22 | 
					PEMBELIAN WERLESSS | 
					1,00 | 
					1 | 
					200.000,00 | 
					200.000,00 | 
					662.602.117,00 | 
					
					| 253 | 
					2025-04-29 | 
					PEMBELIAN CNP 150 | 
					1,00 | 
					1 | 
					5.360.000,00 | 
					5.360.000,00 | 
					667.962.117,00 | 
					
					| 254 | 
					2025-04-29 | 
					PEMBELIAN CNP 125 | 
					1,00 | 
					1 | 
					6.720.000,00 | 
					6.720.000,00 | 
					674.682.117,00 | 
					
					| 255 | 
					2025-04-29 | 
					PEMBELIAN WF 150 | 
					1,00 | 
					1 | 
					1.172.000,00 | 
					1.172.000,00 | 
					675.854.117,00 | 
					
					| 256 | 
					2025-04-29 | 
					PEMBELIAN WD 14" | 
					1,00 | 
					1 | 
					76.000,00 | 
					76.000,00 | 
					675.930.117,00 | 
					
					| 257 | 
					2025-04-29 | 
					PEMBELIAN KAWAT LAS | 
					1,00 | 
					1 | 
					300.000,00 | 
					300.000,00 | 
					676.230.117,00 | 
					
					| 258 | 
					2025-04-29 | 
					PEMBELIAN BASE PLAT UK 10x25x25mm | 
					1,00 | 
					1 | 
					340.000,00 | 
					340.000,00 | 
					676.570.117,00 | 
					
					| 259 | 
					2025-04-29 | 
					PEMBELIAN BASE PLAT UK 10x25x350 | 
					1,00 | 
					1 | 
					924.000,00 | 
					924.000,00 | 
					677.494.117,00 | 
					
					| 260 | 
					2025-04-29 | 
					PEMBELIAN OXIGEN UNTUL BLANDER | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					677.594.117,00 | 
					
					| 261 | 
					2025-04-30 | 
					Beli kopii tukang | 
					1,00 | 
					1 | 
					96.500,00 | 
					96.500,00 | 
					677.690.617,00 | 
					
					| 262 | 
					2025-04-30 | 
					Bel bensin buat campuran cat | 
					1,00 | 
					1 | 
					48.000,00 | 
					48.000,00 | 
					677.738.617,00 | 
					
					| 263 | 
					2025-05-01 | 
					Token listrik 200 | 
					1,00 | 
					1 | 
					202.500,00 | 
					202.500,00 | 
					677.941.117,00 | 
					
					| 264 | 
					2025-05-01 | 
					GEMBOK ATAS | 
					1,00 | 
					1 | 
					50.000,00 | 
					50.000,00 | 
					677.991.117,00 | 
					
					| 265 | 
					2025-05-01 | 
					BELI BENSIN CAMPURAN CAT | 
					1,00 | 
					1 | 
					50.000,00 | 
					50.000,00 | 
					678.041.117,00 | 
					
					| 266 | 
					2025-05-01 | 
					BELI CELENGAN 25PCS | 
					1,00 | 
					1 | 
					108.625,00 | 
					108.625,00 | 
					678.149.742,00 | 
					
					| 267 | 
					2025-05-03 | 
					SEWA SKA FOLDING 10 SET | 
					1,00 | 
					1 | 
					340.000,00 | 
					340.000,00 | 
					678.489.742,00 | 
					
					| 268 | 
					2025-05-04 | 
					SERVIS AC 2 UNIT | 
					1,00 | 
					1 | 
					250.000,00 | 
					250.000,00 | 
					678.739.742,00 | 
					
					| 269 | 
					2025-05-04 | 
					PEMBELIAN CNP 100 | 
					1,00 | 
					1 | 
					5.480.000,00 | 
					5.480.000,00 | 
					684.219.742,00 | 
					
					| 270 | 
					2025-05-04 | 
					PEMBELIAN CNP 150 | 
					1,00 | 
					1 | 
					290.000,00 | 
					290.000,00 | 
					684.509.742,00 | 
					
					| 271 | 
					2025-05-05 | 
					PEMBELIAN WD TIPIS | 
					1,00 | 
					1 | 
					110.000,00 | 
					110.000,00 | 
					684.619.742,00 | 
					
					| 272 | 
					2025-05-05 | 
					PEMBELIAN WD TEBAL | 
					1,00 | 
					1 | 
					175.000,00 | 
					175.000,00 | 
					684.794.742,00 | 
					
					| 273 | 
					2025-05-05 | 
					PEMBELIAN KAWAT LAS | 
					1,00 | 
					1 | 
					298.000,00 | 
					298.000,00 | 
					685.092.742,00 | 
					
					| 274 | 
					2025-05-05 | 
					PEMBELIAN ZIN CROMATE 1 GL | 
					1,00 | 
					1 | 
					257.000,00 | 
					257.000,00 | 
					685.349.742,00 | 
					
					| 275 | 
					2025-05-05 | 
					PEMBELIAN AS DRAT 16 MM | 
					1,00 | 
					1 | 
					12.000,00 | 
					12.000,00 | 
					685.361.742,00 | 
					
					| 276 | 
					2025-05-05 | 
					PEMBELIAN MUR 16 MM | 
					1,00 | 
					1 | 
					36.000,00 | 
					36.000,00 | 
					685.397.742,00 | 
					
					| 277 | 
					2025-05-05 | 
					PEMBRLIAN ZIN CROMATE 3GL | 
					1,00 | 
					1 | 
					771.000,00 | 
					771.000,00 | 
					686.168.742,00 | 
					
					| 278 | 
					2025-05-06 | 
					PEMBELIA MUR BAUT | 
					1,00 | 
					1 | 
					36.000,00 | 
					36.000,00 | 
					686.204.742,00 | 
					
					| 279 | 
					2025-05-08 | 
					PEMBELIAN SEMEN 1 SAK | 
					1,00 | 
					1 | 
					50.000,00 | 
					50.000,00 | 
					686.254.742,00 | 
					
					| 280 | 
					2025-05-08 | 
					PEMBELIAN CNP 125 | 
					1,00 | 
					1 | 
					660.000,00 | 
					660.000,00 | 
					686.914.742,00 | 
					
					| 281 | 
					2025-05-08 | 
					PEMBELIAN CAT ZIN CROMATE 1GL | 
					1,00 | 
					1 | 
					257.000,00 | 
					257.000,00 | 
					687.171.742,00 | 
					
					| 282 | 
					2025-05-10 | 
					PEMBELIAN CAT ZIN CROMATE 1GL | 
					1,00 | 
					1 | 
					257.000,00 | 
					257.000,00 | 
					687.428.742,00 | 
					
					| 283 | 
					2025-05-19 | 
					Bqyar nota material tglb30/4 25 | 
					1,00 | 
					1 | 
					1.330.000,00 | 
					1.330.000,00 | 
					688.758.742,00 | 
					
					| 284 | 
					2025-05-27 | 
					PEMBELIAN GENTENG 2600 PC SM KNOK 96 PCS | 
					1,00 | 
					1 | 
					10.744.000,00 | 
					10.744.000,00 | 
					699.502.742,00 | 
					
					| 285 | 
					2025-05-27 | 
					UPAH PEKERJA 3 ORANG @550.000×18 HARI | 
					1,00 | 
					1 | 
					9.900.000,00 | 
					9.900.000,00 | 
					709.402.742,00 | 
					
					| 286 | 
					2025-05-27 | 
					UPAH BONGKAR GENTENG DR TRUK | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					709.502.742,00 | 
					
					| 287 | 
					2025-05-29 | 
					PEMBELIAN KUAS 1,5 DAN 2" @2 PCS | 
					1,00 | 
					1 | 
					11.027,00 | 
					11.027,00 | 
					709.513.769,00 | 
					
					| 288 | 
					2025-05-29 | 
					PEMBELIAN SIKAT KAWAT 4 " | 
					1,00 | 
					1 | 
					22.454,00 | 
					22.454,00 | 
					709.536.223,00 | 
					
					| 289 | 
					2025-05-29 | 
					DINABOL 10X50 1DUS 150pcs | 
					1,00 | 
					1 | 
					158.775,00 | 
					158.775,00 | 
					709.694.998,00 | 
					
					| 290 | 
					2025-05-29 | 
					CUTTING GERINDA POTONG  1DUS | 
					1,00 | 
					1 | 
					46.922,00 | 
					46.922,00 | 
					709.741.920,00 | 
					
					| 291 | 
					2025-05-29 | 
					KAWQT LAS 2MM 1DUS | 
					1,00 | 
					1 | 
					50.750,00 | 
					50.750,00 | 
					709.792.670,00 | 
					
					| 292 | 
					2025-05-29 | 
					TINER DIRIGENT 5LT | 
					1,00 | 
					1 | 
					84.212,00 | 
					84.212,00 | 
					709.876.882,00 | 
					
					| 293 | 
					2025-05-29 | 
					KAWAT LAS 1,6 2DUS | 
					1,00 | 
					1 | 
					76.100,00 | 
					76.100,00 | 
					709.952.982,00 | 
					
					| 294 | 
					2025-05-29 | 
					CAT PUTIH 4 KALENG | 
					1,00 | 
					1 | 
					179.760,00 | 
					179.760,00 | 
					710.132.742,00 | 
					
					| 295 | 
					2025-05-29 | 
					KONSUMSI KERJA BAKTI | 
					1,00 | 
					1 | 
					135.000,00 | 
					135.000,00 | 
					710.267.742,00 | 
					
					| 296 | 
					2025-05-29 | 
					TINER KALENG | 
					1,00 | 
					1 | 
					20.000,00 | 
					20.000,00 | 
					710.287.742,00 | 
					
					| 297 | 
					2025-05-29 | 
					MATAVBOR BESI 10 | 
					1,00 | 
					1 | 
					115.000,00 | 
					115.000,00 | 
					710.402.742,00 | 
					
					| 298 | 
					2025-06-01 | 
					BELI SARUNG TANGAN 2 BALL | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					710.502.742,00 | 
					
					| 299 | 
					2025-06-01 | 
					ES TEH MANIS HASEL 30 | 
					1,00 | 
					1 | 
					90.000,00 | 
					90.000,00 | 
					710.592.742,00 | 
					
					| 300 | 
					2025-06-03 | 
					UPAH BONGKAR GRANIT | 
					1,00 | 
					1 | 
					150.000,00 | 
					150.000,00 | 
					710.742.742,00 | 
					
					| 301 | 
					2025-06-06 | 
					Bayar tukang reling tangga 3hari | 
					1,00 | 
					1 | 
					570.000,00 | 
					570.000,00 | 
					711.312.742,00 | 
					
					| 302 | 
					2025-06-08 | 
					Beli isamo | 
					1,00 | 
					1 | 
					90.000,00 | 
					90.000,00 | 
					711.402.742,00 | 
					
					| 303 | 
					2025-06-13 | 
					Bayar tukang reling tangga 2 orang 1 hari | 
					1,00 | 
					1 | 
					380.000,00 | 
					380.000,00 | 
					711.782.742,00 | 
					
					| 304 | 
					2025-07-02 | 
					KOPI DAN LAINNYA | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					711.882.742,00 | 
					
					| 305 | 
					2025-07-05 | 
					ONGKOS TUKQNG DAN KENEK 4 HARI | 
					1,00 | 
					1 | 
					1.360.000,00 | 
					1.360.000,00 | 
					713.242.742,00 | 
					
					| 306 | 
					2025-07-06 | 
					KONSUMSI KERJA BAKTI | 
					1,00 | 
					1 | 
					163.000,00 | 
					163.000,00 | 
					713.405.742,00 | 
					
					| 307 | 
					2025-07-12 | 
					BAYAR TUKANG+KENEK 7 HARI | 
					1,00 | 
					1 | 
					2.380.000,00 | 
					2.380.000,00 | 
					715.785.742,00 | 
					
					| 308 | 
					2025-07-14 | 
					SOUND SI5TEM MASJID | 
					1,00 | 
					1 | 
					2.098.000,00 | 
					2.098.000,00 | 
					717.883.742,00 | 
					
					| 309 | 
					2025-07-19 | 
					BAYAR MATERIAL | 
					1,00 | 
					1 | 
					9.375.000,00 | 
					9.375.000,00 | 
					727.258.742,00 | 
					
					| 310 | 
					2025-07-19 | 
					BAYAR TUKANG KENEK 7 HARI | 
					1,00 | 
					1 | 
					2.380.000,00 | 
					2.380.000,00 | 
					729.638.742,00 | 
					
					| 311 | 
					2025-07-20 | 
					KNOK.KABEL.BOR.RODA.KARUNG.KONSUMSI DLL | 
					1,00 | 
					1 | 
					824.000,00 | 
					824.000,00 | 
					730.462.742,00 | 
					
					| 312 | 
					2025-07-20 | 
					PARANET,TALI,KLIP | 
					1,00 | 
					1 | 
					142.000,00 | 
					142.000,00 | 
					730.604.742,00 | 
					
					| 313 | 
					2025-07-26 | 
					BAYAR TUKANG DAN KENEK 7 HARI | 
					1,00 | 
					1 | 
					2.380.000,00 | 
					2.380.000,00 | 
					732.984.742,00 | 
					
					| 314 | 
					2025-07-27 | 
					KOPI.TEHH.GULA TUKANG DAN KERJA BAKTI | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					733.084.742,00 | 
					
					| 315 | 
					2025-07-28 | 
					DP KUBAH | 
					1,00 | 
					1 | 
					10.000.000,00 | 
					10.000.000,00 | 
					743.084.742,00 | 
					
					| 316 | 
					2025-07-28 | 
					UPAH ANGKAT PASIR SLAMET | 
					1,00 | 
					1 | 
					50.000,00 | 
					50.000,00 | 
					743.134.742,00 | 
					
					| 317 | 
					2025-07-30 | 
					BAYAR MATERIAL | 
					1,00 | 
					1 | 
					3.139.000,00 | 
					3.139.000,00 | 
					746.273.742,00 | 
					
					| 318 | 
					2025-08-01 | 
					NO DROP 4 KG | 
					1,00 | 
					1 | 
					201.000,00 | 
					201.000,00 | 
					746.474.742,00 | 
					
					| 319 | 
					2025-08-02 | 
					TUKANG DAN KENEK 3DAN 6 HARI | 
					1,00 | 
					1 | 
					1.440.000,00 | 
					1.440.000,00 | 
					747.914.742,00 | 
					
					| 320 | 
					2025-08-25 | 
					BAYAR MATERIAL | 
					1,00 | 
					1 | 
					2.754.000,00 | 
					2.754.000,00 | 
					750.668.742,00 | 
					
					| 321 | 
					2025-08-30 | 
					CICILAN SPEAKER 2 | 
					1,00 | 
					1 | 
					458.123,00 | 
					458.123,00 | 
					751.126.865,00 | 
					
					| 322 | 
					2025-09-24 | 
					CICILAN KUBAH 1 | 
					1,00 | 
					1 | 
					1.700.000,00 | 
					1.700.000,00 | 
					752.826.865,00 | 
					
					| 323 | 
					2025-09-25 | 
					CiICILAN SPEAKER 3 | 
					1,00 | 
					1 | 
					458.131,00 | 
					458.131,00 | 
					753.284.996,00 | 
					
					| 324 | 
					2025-10-01 | 
					NO DROP PUTIH 4 KG | 
					1,00 | 
					1 | 
					218.700,00 | 
					218.700,00 | 
					753.503.696,00 | 
					
					| 325 | 
					2025-10-01 | 
					Upah cat dan bongkar scafolding | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					753.603.696,00 | 
					
					| 326 | 
					2025-10-10 | 
					CICIL KUBAH 2 | 
					1,00 | 
					900.000 | 
					1,00 | 
					1,00 | 
					753.603.697,00 | 
					
					| 327 | 
					2025-10-18 | 
					KOPI TUKANG | 
					1,00 | 
					1 | 
					50.000,00 | 
					50.000,00 | 
					753.653.697,00 | 
					
					| 328 | 
					2025-10-18 | 
					ONGKOS BM HEBEL | 
					1,00 | 
					1 | 
					20.000,00 | 
					20.000,00 | 
					753.673.697,00 | 
					
					| 329 | 
					2025-10-18 | 
					SOLASI | 
					1,00 | 
					1 | 
					10.000,00 | 
					10.000,00 | 
					753.683.697,00 | 
					
					| 330 | 
					2025-10-18 | 
					UPAH TUKANG2 KENEK 1 3HARI | 
					1,00 | 
					1 | 
					1.370.000,00 | 
					1.370.000,00 | 
					755.053.697,00 | 
					
					| 331 | 
					2025-10-19 | 
					KONSUMSI KERJA BAKTI | 
					1,00 | 
					1 | 
					100.000,00 | 
					100.000,00 | 
					755.153.697,00 | 
					
					| 332 | 
					2025-10-19 | 
					SEMEN 3 RODA 4,ACIAN PUTI 3RODA 2 | 
					1,00 | 
					1 | 
					590.000,00 | 
					590.000,00 | 
					755.743.697,00 | 
					
					| 333 | 
					2025-10-21 | 
					FITING LAMPU 6 | 
					1,00 | 
					1 | 
					40.000,00 | 
					40.000,00 | 
					755.783.697,00 | 
					
					| 334 | 
					2025-10-22 | 
					KEENI 1/2,LEM,SAMBUNGAN,PAKU PARALAON | 
					1,00 | 
					1 | 
					54.000,00 | 
					54.000,00 | 
					755.837.697,00 | 
					
					| 335 | 
					2025-10-24 | 
					LQMPU 60 W 3 BIJI | 
					1,00 | 
					1 | 
					255.000,00 | 
					255.000,00 | 
					756.092.697,00 | 
					
					| 336 | 
					2025-10-25 | 
					KABEL TOA 2 ROLL | 
					1,00 | 
					1 | 
					800.000,00 | 
					800.000,00 | 
					756.892.697,00 | 
					
					| 337 | 
					2025-10-25 | 
					KABEL TOA 15M | 
					1,00 | 
					1 | 
					120.000,00 | 
					120.000,00 | 
					757.012.697,00 | 
					
					| 338 | 
					2025-10-25 | 
					KENI L PIPA KABEL 20 PCS | 
					1,00 | 
					1 | 
					8.000,00 | 
					8.000,00 | 
					757.020.697,00 | 
					
					| 339 | 
					2025-10-25 | 
					SANBUNGAN PIPA,KLEM PIPA KABEL | 
					1,00 | 
					1 | 
					70.000,00 | 
					70.000,00 | 
					757.090.697,00 | 
					
					| 340 | 
					2025-10-25 | 
					NO DROP 1 KG PUTIH | 
					1,00 | 
					51 | 
					50.500,00 | 
					50.500,00 | 
					757.141.197,00 | 
					
					| 341 | 
					2025-10-25 | 
					NO DROP 1 KG PUTIH | 
					1,00 | 
					51 | 
					50.500,00 | 
					50.500,00 | 
					757.191.697,00 | 
					
					| 342 | 
					2025-10-25 | 
					TE DUS 20 PCS | 
					1,00 | 
					1 | 
					33.000,00 | 
					33.000,00 | 
					757.224.697,00 | 
					
					| 343 | 
					2025-10-25 | 
					UPAH TUKQNG 2 KENEK 1 6 HARI | 
					1,00 | 
					1 | 
					3.000.000,00 | 
					3.000.000,00 | 
					760.224.697,00 | 
					
					| 344 | 
					2025-10-27 | 
					STOP KRAN 3/4  DAN ISOLATIP | 
					1,00 | 
					1 | 
					29.500,00 | 
					29.500,00 | 
					760.254.197,00 | 
					
					| 345 | 
					2025-10-28 | 
					BENANG TUKANG 15 | 
					1,00 | 
					1 | 
					20.000,00 | 
					20.000,00 | 
					760.274.197,00 | 
					
					| 346 | 
					2025-11-01 | 
					KERAMIK 60X60 13 D | 
					1,00 | 
					1 | 
					1.731.600,00 | 
					1.731.600,00 | 
					762.005.797,00 | 
					
					| 347 | 
					2025-11-01 | 
					BAYAR MATERIAL | 
					1,00 | 
					1 | 
					4.000.000,00 | 
					4.000.000,00 | 
					766.005.797,00 | 
					
					| 348 | 
					2025-11-01 | 
					UPAH 2 TUKANG 6 HARI | 
					1,00 | 
					1 | 
					2.220.000,00 | 
					2.220.000,00 | 
					768.225.797,00 | 
					
					| 349 | 
					2025-11-01 | 
					UPAH KENEK 6 HARI | 
					1,00 | 
					1 | 
					780.000,00 | 
					780.000,00 | 
					769.005.797,00 | 
					
					| 350 | 
					2025-11-01 | 
					BELI PASIR PUTIH 1 ENGKEL JOMPLANG | 
					1,00 | 
					1 | 
					1.600.000,00 | 
					1.600.000,00 | 
					770.605.797,00 | 
					
					| 351 | 
					2025-11-01 | 
					PERBAIKAN LISTRIK | 
					1,00 | 
					1 | 
					130.000,00 | 
					130.000,00 | 
					770.735.797,00 | 
					
 |  | T o t a l |  |  |  |  | 770.735.797,00 |  |